Koralm Railway Site Supervision Lot 60.3: Breakthrough at the Untersammelsdorf Tunnel
Following on from extensive piling (1141 piles) and jet grouting (7980 grout pillars), the top heading was completed on 26th April 2018. The bench and invert drives for the Untersammelsdorf Tunnel are also approaching completion. All works continue to be free of accidents. Concreting works in the cut-and-cover Srejach Tunnel have also been completed. Progress at the infill sites is as follows: